Bosque County — Texas
A negative-control record separating a marketed 1 GW power headline from the current normalized usable-capacity state and its milestone path.
State
Milestone path
ICA available: 2026 Q2 → CIAC due: 2026 Q3 → energization targeted: 2029 Q3 → compute deployment.
Interpretation: The normalized record does not treat the 1 GW headline as current usable compute capacity.
Dependency chain
Marketed capacity → interconnection agreement → CIAC → grid/infrastructure execution → energization → compute deployment → revenue.
The existing research artifact contains delay-risk diagnostics, but those probabilities are explicitly uncalibrated and are not reproduced here as empirical forecasts.
Evidence
EV-FIE005B-008-001 — Bosque County transaction-grade assessment, recorded 2026-09-15.
Source: Quiet Stance internal research artifact. The page preserves the distinction between public headline claims and normalized state.
What remains unknown
Final interconnection timing, construction execution, energization timing, and compute deployment timing remain unresolved in this public record.