Capacity state

Headline capacity1000 MW
Normalized usable capacity0 MW
Usable ratio0.0%
Compute-readynot established

Economic context

Target energization2029-Q3

Dependencies

interconnection agreement; CIAC payment; grid/infrastructure execution; energization; compute deployment

Evidence

EV-FIE005B-008-001
Bosque County transaction-grade assessment
Recorded 2026-09-15

Supports: 1,000 MW marketed capacity; 0 MW current usable capacity in the normalized dataset; target energization Q3 2029; ICA/CIAC dependency chain

Open the public evidence registry →

Unknowns

final interconnection timing; construction execution; energization timing; compute deployment timing

Next action

Defined path